Archives

Category: Go-go-go 555
  • Ashiba adventure

    Ashiba adventure

    555 is surrounded! From the wooden fence erected during the foundation work, we moved on to proper scaffolding this week. It’s called ashiba in Japanese, which means legs. When I saw it yesterday, it was all I could do not to scurry up that staircase to the top. I restrained myself, though I’m not actually…

    Read the full post

  • The view from 45 cm up

    The view from 45 cm up

    Our foundations are unusually tall for a modern building; they are much more like the vernacular kominka of old when high floors kept the dirt and animals out. At 45 cm (18 in), our floor floats so far above ground level that there will be two steps up into the house from the doma. The…

    Read the full post

  • Pre-cut

    Pre-cut

    Yesterday afternoon, the wood arrived! It was three trucks’ worth of lumber – beams, posts, rafters, gables, studs, joists – all of the fundamental framing parts. Next Friday every stick of it will be put into place for the jotoshiki. These hundreds of timbers have been precision milled. They are pre-cut to length as well…

    Read the full post

  • Hokora, the little shrine

    Hokora, the little shrine

    Sakaguchi-san came on Sunday, his day off, to work on something that I know has been bugging him: getting the hokora (祠), our little shrine, back in place. When we started the gabion work, Kawasaki-san disassembled and moved the shrine to the shed. There was too much chance of it being damaged by big equipment…

    Read the full post

  • Nama-con #3

    Nama-con #3

    Yesterday was the final pour of concrete for the foundations. It is such a treat to watch the coordinated mayhem of professionals doing their well-understood roles in a project. Six men worked together to fill all of the oiled framework for the riser ring (thanks for the correct terminology, Mark). One operated the cement mixer.…

    Read the full post

  • Nama-con #2

    Nama-con #2

    Today the rest of the slab was poured. It went in over rebar that had been built over the course of the week. Frames on the side hold it in place until it dries. Each stage of the process makes the house feel more real – literally concrete instead of an abstraction. In addition to…

    Read the full post

  • Glass house

    Glass house

    I sort of don’t want a house at all. I want this beautiful open space where I can look in all directions at my surroundings. Like Hitomi and I did yesterday when we laid down in the future bedroom. I am glad Kengo snapped that photo of us. When the house goes up, I lose…

    Read the full post

  • Lighting design

    Lighting design

    I have put off a big part of the 555 planning, and that is lighting. Included in our quote is a basic lighting setup but even as I agreed to it, I knew it was inadequate. I like lights and this house has potential for interesting lighting inside and out. Friends recommended that I look…

    Read the full post

  • Tile Mines, phase 3

    Tile Mines, phase 3

    Trick? Treat? I’m not sure yet. My Halloween was spent moving all of the tiles I sorted last year from Hangar eight up to 555. There are seven pallets, a dozen trays, at least 8 bags, and a wheelbarrow. They occupy the spot where the old outhouse used to stand. It is literally tons of…

    Read the full post

  • Nama-con #1

    Nama-con #1

    Yesterday was the first pour of concrete. This is just a few centimeters deep to form a base for the rebar and the 2nd pour of the pad. Those will be done at the end of next week. From now until Friday, the concrete sets and there’s not much else to see. This first pour…

    Read the full post